Which chart is used to illustrate a project schedule and includes details of start and finish dates?

Pie chart

Line chart

Bar chart

Gantt chart

A Gantt chart is specifically designed to illustrate a project schedule, making it an invaluable tool in project management. It visually represents the start and finish dates of tasks or activities within a project, displayed along a timeline. The horizontal bars that extend from the start date to the finish date of each task allow stakeholders to easily see the duration of tasks and how they overlap with one another.

In addition to showing the timing of tasks, Gantt charts can also include information about task dependencies, which can help in understanding how delays in one task might affect others. This visualization helps project managers to monitor progress at a glance and make adjustments as necessary to keep the project on track. Overall, Gantt charts offer a clear and effective way to communicate project schedules, making them widely used in project planning and management.

Get further explanation with Examzify DeepDiveBeta
Next Question

Report this question

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy